Half-term

13/02/2016

Half term is now here. We are delighted that our contractors, North Eastern Plant have been able to make such good progress on the new developments at the Park. Our thanks go to Charlie and Jim, and their staff, who have cleared and renovated the foundations of three blocks of aviaries, installed new services, excavated and repaired roadways and fully renovated and repaired our car-parks - all in the space of less than a month! The entire animal collection at Hamerton can now be viewed from hard tarmac paths and roadways. The whole site is accessible without steps or other barriers. Work will now continue in house on enclosures to house many new animals due to arrive at Hamerton later in the spring this year. We know that March will bring drying winds as always, and then N.E.Plant will be able to resume their works on our new Malaysian Tiger enclosure which is due for completion by early summer. Further details will be posted here, and on 'Facebook' and 'Twitter' as works progress.